June 14, 2007
Construction – On Schedule
Construction in all areas continues to move forward. The weather has been cooperating and many workers have been putting in long hours.
Track Master has installed the main line and is beginning to work on the rail spurs. They continue to be on schedule.
Pipe fitters are running full speed and are also on schedule.
Aquilla is providing the gas line for our plant, they have arrived on sight and are beginning to install the line.
The Administration building is now complete and they are working on getting the communications, air conditioning and plumbing finished.
Stainless steel tanks are being built on site and construction is going well.
Reding’s will begin installation of the sewer line next week.
Reising Protective Coating will be sandblasting and priming all of the carbon steel tanks.
Dan Muller, Construction Representative for the Board of Directors