01/08/2007
Construction continues to go well with the completion of the following:
§ Tank Farm Foundations
§ Pipe Bridge foundation
§ Storage Yard Building
§ Erection of the precast inside the Processing building
§ Forming and pouring of support building foundation
Near completed projects include:
§ Installation of pretreatment underground utilities
§ Installation of outside underground utilities
§ Forming and pouring of support building foundation
§ Erecting the process building structural steel
Projects starting soon include:
§ Construction of Truck Scale
§ Field built Tanks
§ Installation of pipe bridges
The framing and enclosure of the Administration Building will begin this week.
Dan Muller, Construction Representative for the Board of Directors